How often does a county project worth $21 million reach the start of construction with every dollar already in hand, no bond election and no tax increase? Andrews County is in that position with its new recreation center near Andrews Middle School. The building still hasn't broken ground, and earlier this month the county moved to hire a construction manager because, in officials' own words, "we feel we're behind."
Money held this project up for most of the last decade. The schedule holds it up now. Seeing that change explains the October decision, the street work planned for northwest Andrews, and why the current rec center in northeast Andrews still has more seasons ahead of it.
The rec center has been talked about in Andrews for more than 10 years. According to the Andrews County News, the real push came in the last two to three years.
The funding came together in two steps. In July 2025, the county had $15 million set aside and was applying for a $5 million grant from the F. Marie Hall Foundation. At that point the application was still pending. The grant came through. As of the October 9, 2026 issue of the Andrews County News, the county counts $21 million available for the project, with the grant described as the piece that got it to that figure.
County officials described what that means for taxpayers in the Andrews County News:
"We don't have to do a bond or anything with taxes. We saved the money, and with the grant, we'll get there faster and have a nicer facility than what we would have had."
The county also bought the land ahead of time. It paid $200,000 for the property at 408 NW Ave. D and $130,000 for three lots at 411 NW Ave. D for extra parking. The site, the cash, the architect and the contractor were all lined up by early summer. Only the start date was left.
The project's own milestones show how the expected start has moved this year.
| When | What was reported | Source |
|---|---|---|
| June 2026 | Commissioners approved BKV Architects to produce final design renderings in 12 weeks. Groundbreaking could come "later in the summer; around the time the next school year begins." | Andrews County News, June 16, 2026 |
| July 2026 | Commissioners approved the NW Ave. E street expansion. Groundbreaking was still expected later that summer or around the start of school. | Andrews County News, July 31, 2026 |
| October 2026 | Commissioners approved seeking proposals for a construction manager. Groundbreaking estimated "sometime in coming months." | Andrews County News, October 9, 2026 |
School started and the target passed without a groundbreaking. As of the October report, the architects were still finishing the final renderings. After that, Lee Lewis Construction will seek bids from subcontractors before work begins. Each step has to finish before the next one starts, so a few weeks lost at the design stage push everything after it back.
This is where the October decision comes in. A construction manager adds nothing to the building itself. The job is about time and money. Here is how county officials described the role in the Andrews County News:
With no bond to sell and no grant left to win, the remaining work is turning money already in hand into a building on schedule. The county will take proposals for a set period, open them at a future commissioners court meeting and then award the role.
The titles have also changed. In June, the Andrews County News called Lee Lewis Construction the "Construction Manager." By October, the same paper described Lee Lewis as the contractor, with a separate construction manager now being hired to oversee it and BKV. The October setup is the current one.
Neighbors around the middle school will see the effects of the new building on their streets before they see the building.
In July, commissioners approved a new one-way stretch of NW Ave. E north of the future rec center. The guaranteed maximum price is $439,434, paid from the county's Capital Improvement Fund. The new stretch of NW Ave. E will replace the section of NW Ave. D next to the rec center, and that section of NW Ave. D will close once the new facility opens.
The October report calls the street work a required part of the project and says it is "progressing." No start or completion date for the road work has been reported. Under the plan as approved, the closure of NW Ave. D is tied to the building opening, so the drive past the middle school stays as it is until then.
The design explains why the delay matters to families. Plans call for three gyms, a walking track, a virtual-reality room and space for recreation programs. County officials told the Andrews County News they want "something for everyone from two years old to 90."
The three gyms carry the most weight. According to the Andrews County News, the county currently doesn't have enough gym space for its youth recreation programs. Officials see more gyms as the answer for youth programs, with adult leagues becoming possible too. The walking track and program space suggest a building meant for daily use, beyond league nights. Until the new gyms open, youth programs keep running out of the current facility.
The new building will replace the county's current recreation facility in northeast Andrews, which is about 60 years old. The county directory lists the Youth Recreation Center at 300 NE 6th Street. Its lobby and office and its game room both keep the same hours:
Youth sign-ups are already open for the coming season. The county's online recreation catalog lists a 2026-27 Boys Basketball league for ages 6 to 11. It's split into 6–7, 8–9 and 10–11 age groups, costs $40, and lists location and times for each group as to be determined. You'll find registration in the Andrews County recreation catalog.
Officials expect the build to take a year to a year and a half once it starts. If ground broke this winter, that range would put an opening somewhere between late 2027 and 2028. The 2026-27 basketball season will be played without the new gyms either way. For now, the commissioners court meeting where the construction manager proposals are opened is the next date to watch, followed by the release of the final renderings.
For more on everyday life in town, the Andrews neighborhood page collects local context in one place.
If you live near NW Ave. D or the middle school and want to talk through how the road changes and new rec center could affect your street, I'm glad to help. I follow Andrews closely and am always happy to share what I'm seeing. Krista Maddox is just a message away. Let's Connect.